Homes
60,846Social rented, 2024-25
Their repair target
20 daysNon-emergency, their own
Failing decency
0.4%Median housing association: 0.2%

What stands out in Southern Housing's figures

A low stock condition figure, with the usual caveat

Southern Housing reported 0.4% of homes failing the Decent Homes Standard, below the housing association median of 0.2%. Worth knowing that landlords assess their own stock and the regulator publishes what it receives without auditing it, so a low figure can mean good homes or can mean not every home has been surveyed.

A tight repair target of 20 days

Tighter than the median of 28 days, which makes the hit rate the number that matters: Southern Housing completed 72.9% of non-emergency repairs inside it. A demanding target missed often tells you something different from a generous target met.

These scores came from a telephone survey

The regulator cautions against comparing landlords on individual measures without allowing for how the survey was run. Southern Housing's was predominantly telephone, and method affects who answers: telephone surveys tend to reach people who pick up to an unknown number. Region, tenant age and the share of supported housing all move these numbers too.

One of the largest landlords in this data

60,846 social rented homes, with only 5 of the 179 landlords here larger. At this size a single percentage point is about 608 homes, so small-looking differences in the table below are large numbers of real households, and an organisation this big is rarely uniform across its stock.

Which benchmark you use changes the answer

Against the all-landlord median of 0.5% in the table below, Southern Housing's 0.4% looks good. Against other housing associations, where the median is 0.2%, it looks poor. Councils and associations are not alike on stock condition and the housing association figure is the fairer comparison here.

What binds them regardless

Everything above is Southern Housing measuring itself against its own promises. Awaab's Law is different, because it is law and it overrides them. Emergency hazards: 24 hours to investigate and make safe. Damp or mould posing a significant risk of harm: 10 working days to investigate, a written summary within 3 working days of finishing, safety work started within 5. When the clock actually starts.

Southern Housing's 2024-25 return in full

MeasureSouthern HousingSector median
Emergency repairs inside their own target 80.1%
14.8 points worse than the median
94.9%
Non-emergency repairs inside their own target 72.9%
9.6 points worse than the median
82.5%
Satisfaction with the repairs service 65.3%
8.3 points worse than the median
73.6%
Satisfaction with time taken on the last repair 61.5%
8 points worse than the median
69.5%
Stage 2 complaints answered in time 85.9%
3 points worse than the median
88.9%
Satisfaction with the approach to complaints 33.1%
2.4 points worse than the median
35.5%
Stage 1 complaints answered in time 88.7%
1.2 points worse than the median
89.9%
Satisfaction that the home is well maintained 71.5%
about the same as the median
71.9%
Satisfaction that the home is safe 78%
about the same as the median
77.6%
Homes not meeting the Decent Homes Standard 0.4%
about the same as the median
0.5%
137 landlords reported worse Non-decent homes, every landlord ranked

If a repair is not happening

Put it in writing and keep the reference, because that date is what every later deadline counts from. If nothing moves, make a formal complaint rather than another chaser. They must acknowledge within 5 working days and respond within 10 of that, then stage two must be handled by someone not involved first time and answered within 20 working days.

How housing association complaints work, and after that the Housing Ombudsman Service, which is free, can order the repair as well as compensation, and takes no percentage. What to ask before signing with anyone.

If it is damp or mould Start here, whoever your landlord is

Common questions

What is Southern Housing's target for a repair?

20 days for a non-emergency responsive repair, and 6 hours for an emergency. They met the non-emergency target 72.9% of the time in 2024-25. The median target across the 178 landlords we hold data for is 28 days.

This is their own service target, not a legal deadline. The law requires repairs in a reasonable time, which is not defined and depends on the problem.

How many Southern Housing homes fail the Decent Homes Standard?

250 of 60,846, which is 0.4%. The median housing association reported 0.2%.

These are self-reported figures and the regulator publishes them without auditing them, so they are a reasonable basis for a question and a poor basis for a conclusion. Every landlord ranked on this measure.

What if Southern Housing misses a deadline?

Complain formally, using the words "I am making a formal complaint", then escalate to stage two, then take it to the Housing Ombudsman Service. All three are free and you keep every penny of any award.

Do these figures measure damp and mould?

No. There is no damp and mould measure anywhere in the Tenant Satisfaction Measures, for this landlord or any other. Damp can make a home fail the Decent Homes Standard through the hazard route, but nothing here counts damp cases.

Figures contain public sector information licensed under the Open Government Licence v3.0. Source: Regulator of Social Housing, Tenant Satisfaction Measures 2024-25 (v1.1), published 4 November 2025. Reported by the landlord for the year to 31 March 2025 and not independently audited.