We are not solicitors. This site is free information only. We do not take claims, we do not pass your details to anyone, and we never ask you to sign anything. Who we are

Platform Housing: damp and repairs

What Platform Housing Group Limited publishes about its own performance, the deadlines that bind it, and the free routes when repairs stall.

This page applies to England. The law is different in Wales, where Awaab's Law does not apply at all. See our Wales guidance.

Homes
41,429Social rented, 2024-25
Their repair target
28 daysNon-emergency, their own
Failing decency
0.1%Median housing association: 0.2%

What stands out in Platform Housing's figures

A low stock condition figure, with the usual caveat

Platform Housing reported 0.1% of homes failing the Decent Homes Standard, below the housing association median of 0.2%. Worth knowing that landlords assess their own stock and the regulator publishes what it receives without auditing it, so a low figure can mean good homes or can mean not every home has been surveyed.

Roughly 4 in every 10 routine repairs missed the deadline

Platform Housing completed 62.3% of non-emergency repairs within its own 28-day target, against a sector median of 82.5%. If your repair has run past that point, you are not an unlucky exception, and saying so plainly in a complaint is reasonable.

Emergencies get handled, routine repairs drift

98.2% of emergency repairs were completed in target against 62.3% of non-emergency ones, a gap of 36 points. That pattern usually means resource is being pulled towards whatever is on fire, which is cold comfort if your problem is the slow kind that only becomes an emergency later.

These scores came from a telephone survey

The regulator cautions against comparing landlords on individual measures without allowing for how the survey was run. Platform Housing's was predominantly telephone, and method affects who answers: telephone surveys tend to reach people who pick up to an unknown number. Region, tenant age and the share of supported housing all move these numbers too.

One of the largest landlords in this data

41,429 social rented homes, with only 12 of the 179 landlords here larger. At this size a single percentage point is about 414 homes, so small-looking differences in the table below are large numbers of real households, and an organisation this big is rarely uniform across its stock.

What binds them regardless

Everything above is Platform Housing measuring itself against its own promises. Awaab's Law is different, because it is law and it overrides them. Emergency hazards: 24 hours to investigate and make safe. Damp or mould posing a significant risk of harm: 10 working days to investigate, a written summary within 3 working days of finishing, safety work started within 5. When the clock actually starts.

Platform Housing's 2024-25 return in full

MeasurePlatform HousingSector median
Non-emergency repairs inside their own target 62.3%
20.2 points worse than the median
82.5%
Satisfaction with time taken on the last repair 60%
9.5 points worse than the median
69.5%
Stage 1 complaints answered in time 98.2%
8.3 points better than the median
89.9%
Satisfaction that the home is well maintained 64.8%
7.1 points worse than the median
71.9%
Satisfaction with the repairs service 67.8%
5.8 points worse than the median
73.6%
Emergency repairs inside their own target 98.2%
3.3 points better than the median
94.9%
Stage 2 complaints answered in time 87%
1.9 points worse than the median
88.9%
Satisfaction that the home is safe 75.9%
1.7 points worse than the median
77.6%
Satisfaction with the approach to complaints 34.4%
1.1 points worse than the median
35.5%
Homes not meeting the Decent Homes Standard 0.1%
about the same as the median
0.5%
153 landlords reported worse Non-decent homes, every landlord ranked

If a repair is not happening

Put it in writing and keep the reference, because that date is what every later deadline counts from. If nothing moves, make a formal complaint rather than another chaser. They must acknowledge within 5 working days and respond within 10 of that, then stage two must be handled by someone not involved first time and answered within 20 working days.

How housing association complaints work, and after that the Housing Ombudsman Service, which is free, can order the repair as well as compensation, and takes no percentage. What to ask before signing with anyone.

If it is damp or mould Start here, whoever your landlord is

Common questions

What is Platform Housing's target for a repair?

28 days for a non-emergency responsive repair, and 24 hours for an emergency. They met the non-emergency target 62.3% of the time in 2024-25. The median target across the 178 landlords we hold data for is 28 days.

This is their own service target, not a legal deadline. The law requires repairs in a reasonable time, which is not defined and depends on the problem.

How many Platform Housing homes fail the Decent Homes Standard?

27 of 41,429, which is 0.1%. The median housing association reported 0.2%.

These are self-reported figures and the regulator publishes them without auditing them, so they are a reasonable basis for a question and a poor basis for a conclusion. Every landlord ranked on this measure.

What if Platform Housing misses a deadline?

Complain formally, using the words "I am making a formal complaint", then escalate to stage two, then take it to the Housing Ombudsman Service. All three are free and you keep every penny of any award.

Do these figures measure damp and mould?

No. There is no damp and mould measure anywhere in the Tenant Satisfaction Measures, for this landlord or any other. Damp can make a home fail the Decent Homes Standard through the hazard route, but nothing here counts damp cases.

Figures contain public sector information licensed under the Open Government Licence v3.0. Source: Regulator of Social Housing, Tenant Satisfaction Measures 2024-25 (v1.1), published 4 November 2025. Reported by the landlord for the year to 31 March 2025 and not independently audited.